Finished view of clarifier number one
Two coats of epoxy and one coat of urethane were applied
Finished view of clarifier number two
Three coats of epoxy were applied to the submerged steel
Exterior of the clarifier
The Rend Lake Water Treatment Plant involved abrasive blasting and the recoating of four existing final clarifier basins along with modificiation inside and outside of the existing water plant at Rend lake in central Illinois. This work was completed in two seasons, with the plant only allowing one vessel out of service at a time.
Prepping and painting the Rend Lake Water Treatment Plant
Client:
Rend Lake Conservancy District
Size:
110,000 sq ft
Year completed:
2010
Dollar value:
$610,003
Javascript is required to view this map.
Rend Lake, IL