View looking up from the middle of the 280 foot shaft
Construction of lift-station building
The first of three floors being erected
Two coats of epoxy were brushed and rolled to structural steel
Exterior of lift station close to completion
Working in a 300-feet deep shaft is hard enough. But when you have to work in two, well, it becomes twice as difficult. And that's exactly the scope of work we encountered at the Lower Meramec Lift Station.
In one shaft, we had to apply a concrete lining system at more than 180 mils. And in the other shaft, we had to paint three coats to piping, sometimes as large as five feet in diameter.
Yet again, we're proud to say we completed something that had never been done before with no injuries and on time.
Prepping, painting and protecting the Lower Meramec Lift Station
Client:
Metropolitan St. Louis Sewer District
Size:
190,000 sq ft
Year completed:
2007
Dollar value:
$602,621
Javascript is required to view this map.
St. Louis, MO